ACMS (Automated Continuous Monitoring System) is an IoT system that watches a building's fire fighting installations around the clock and reports their status to a cloud server. In Maharashtra it is required for buildings listed in section 45(1) of the Fire Prevention and Life Safety Measures Act under section 3(3A), with the technical Appendix in force from 12 June 2025. In Delhi, rule 37 of the Delhi Fire Service Rules 2010, as amended, requires it for the occupancies in rule 27(2) to (12) from 24 August 2026.

Updated 2026-10-08 · By the Siya Habitats fire safety engineering team, Nagpur · Every rule cited to its source

What is an automated continuous monitoring system (ACMS)?

An automated continuous monitoring system, or ACMS, is an Internet of Things (IoT) system fitted to a building's fire fighting installations so that their condition is known at all times, not only on the day of an inspection. Sensors and contacts on pumps, tanks, risers, the fire alarm panel and fans feed an IoT gateway. The gateway uploads the data to a cloud server, which sends the status to the owner or occupier and to the agency responsible for the system.

Both Maharashtra and Delhi now describe ACMS in almost identical words. The Maharashtra Appendix says the system shall be provided for both active and passive measures, ensuring that the fire prevention and life safety measures are in good repair and efficient working condition. Delhi's schedule uses the same sentence. The aim is simple: a tripped jockey pump, a dry overhead tank or a dead panel battery should show up on a screen the moment it happens, instead of during a fire.

ACMS does not replace the fire alarm system, the pumps or the periodic certificates. It sits on top of them and keeps a digital record of their health.

Which rules require ACMS, and from when?

In Maharashtra the legal basis is section 3(3A) of the Maharashtra Fire Prevention and Life Safety Measures Act, 2006, inserted by the Amendment Act of 2023 (Mah. XXIV of 2023, gazette of 11 May 2023). It requires the owner, or the occupier where the owner is not traceable, of a building specified under section 45 to provide the fire fighting systems with an automated continuous monitoring system as may be prescribed, certified by a Licensed Agency.

The prescription came with the Maharashtra Fire Prevention and Life Safety Measures (Amendment) Rules, 2025, published on 12 June 2025 (Urban Development Department notification No. MFS-2023/C.R.370/UD-14). New rule 3A says the ACMS shall be as specified in the Appendix, and the Appendix sets out what must be monitored and how. New rule 4(3) and 4(4) add two certificates, Form A-1 and Form B-1.

In Delhi the basis is rule 37 of the Delhi Fire Service Rules, 2010, as amended by the Delhi Fire Service (Amendment) Rules 2025, published in the Delhi Gazette Extraordinary Part IV, No. 143, on 26 May 2026. Rule 1 of the amendment says the changes to rules 34 to 38 and the First and Seventh Schedules come into force 90 days after publication, which places the ACMS rule in force from 24 August 2026. Applications pending on that date are processed under the earlier provisions.

ACMS legal basis at a glance
MaharashtraDelhi
Parent lawFire Prevention and Life Safety Measures Act 2006, section 3(3A) (inserted 2023)Delhi Fire Service Act 2007 with Delhi Fire Service Rules 2010
Detailed ruleRules 2009, rule 3A and the Appendix (inserted 2025)Rules 2010, rule 37 and the ACMS schedule (amended 2025)
GazettePart IV-B, 12 June 2025Part IV, No. 143, 26 May 2026
In force12 June 2025, Phase I with immediate effect24 August 2026 (90 days after publication)
Buildings coveredBuildings listed in section 45(1)Occupancies in rule 27(2) to (12)
CertificatesForm A-1 on installation, Form B-1 every January and JulyRule 37 refers to rule 38(1); no separate ACMS form in the rule text

Which buildings need ACMS in Maharashtra?

Section 3(3A) applies to the buildings specified under section 45, which is the same list of buildings that must appoint a fire officer or fire supervisor. The same list also triggers the Section 45A fire and life safety audit every two years, so these buildings carry all three duties together.

  • Buildings more than 30 m high used as a hotel, hospital, business, mercantile or mixed occupancy of any kind (section 45(1)(a)).
  • Residential buildings more than 70 m high (section 45(1)(b)(1)).
  • Large oil and natural gas installations such as refineries, LPG bottling plants and similar facilities (section 45(1)(b)(2)).
  • Industrial buildings with moderate hazard activities and a built-up area of 30,000 square metres or more, and those with high hazard activities and 10,000 square metres or more (section 45(1)(b)(3)).

A residential tower between 30 m and 70 m is not on the section 45(1) list, so section 3(3A) does not by itself require ACMS there. Its Form B duty still applies.

Which buildings need ACMS in Delhi?

Delhi rule 37 applies to the classes of occupancies identified in sub-rules (2) to (12) of rule 27. That is a much wider net than Maharashtra's, because rule 27 is the list of buildings likely to cause a risk of fire for which a fire safety certificate is needed. Only pandals, sub-rule (1), are left out.

  • Residential buildings, other than hotels and guest houses, more than 15 m high or with five or more storeys.
  • Hotels and guest houses more than 12 m high or with four or more storeys.
  • Educational and institutional buildings more than 9 m high or with three or more storeys.
  • All assembly buildings.
  • Business buildings more than 15 m high or with five or more storeys.
  • Mercantile buildings more than 9 m high or with three or more storeys.
  • Industrial and storage buildings with a covered area on all storeys of more than 250 square metres.
  • Hazardous buildings with a covered area on all storeys of more than 100 square metres.
  • Underground structures with two or more levels.

Storey counts in rule 27 include mezzanine and stilt floors above ground level. The proviso to rule 37 adds that the ACMS shall comply with technical standards and cyber security protocols as the Director may notify.

What must an ACMS monitor?

The Maharashtra Appendix and the Delhi schedule list the same systems and the same mode of integration for each parameter. The table below follows the Maharashtra list; the Delhi text matches it item for item. The mode of integration column is what tells an engineer how each signal is picked up.

ACMS monitoring parameters, Maharashtra Appendix (2025) and Delhi rule 37 schedule
SystemParameterMode of integrationMaharashtraDelhi
HydrantMain hydrant pump run statusWater differential pressure switchRequiredRequired
HydrantStandby diesel or electric pump run statusWater differential pressure switchRequiredRequired
HydrantJockey pump run statusWater differential pressure switchRequiredRequired
HydrantBooster pump run statusWater differential pressure switchRequiredRequired
HydrantPower to jockey pump and to main booster pump (on or off)Listed as a status item; no mode given in the integration tableRequiredRequired
HydrantPower to main hydrant pumpVoltage sensor at the motor control centreRequiredRequired
HydrantHydrant riser low pressurePressure switch or transmitterRequiredRequired
HydrantDiesel tank low levelLevel sensorRequiredRequired
SprinklerMain sprinkler pump run statusWater differential pressure switchRequiredRequired
SprinklerPower to main sprinkler pumpVoltage sensor at the motor control centreRequiredRequired
SprinklerSprinkler riser low pressure (below 5 bar)Pressure switch or transmitterRequiredRequired
Fire water tankUnderground or above ground tank levelUltrasonic water level deviceRequiredRequired
Fire water tankOverhead tank low levelUltrasonic water level deviceRequiredRequired
DetectionDetection operation status, panel or repeater status, panel batteryPotential free contacts from the fire panelRequiredRequired
Manual call pointsOperation statusPotential free contacts from the fire panelRequiredRequired
Public addressPA system working or faultFault status from the PA panelRequiredRequired
Air pressurisationStaircase and lift lobby or hoistway pressurisation fan run statusAir differential pressure switchRequiredRequired
VentilationBasement supply and exhaust fan run statusAir differential pressure switchRequiredRequired

The gazette text prints the panel contacts as 'Plain Old telephone Service (POTS) free contacts'. In practice these are the panel's potential free relay outputs.

How is ACMS data reported?

Both states set out the same procedural requirements. Status is collected on an IoT gateway, uploaded to a cloud server, and sent in real time to the owner or occupier and to the system installer by email, SMS or a mobile app. The cloud portal must offer data reports and alarm reports, so the record of the fire system's health is kept digitally.

ACMS reporting requirements in both states
RequirementWhat the rule says
InputsMinimum digital and analog inputs depending on the system
ProtocolMachine to machine communication over MQTTS to the cloud portal in real time
Connectivity4G, 5G, Ethernet, Wi-Fi or another reliable medium, with data received from the gateway at every 1 minute interval
Loss of dataThe cloud sends an SMS alarm if no data arrives from the gateway for more than 15 minutes
Gateway powerUPS backed, with up to 7 hours of backup in a power failure
Gateway memoryStores at least 10,000 event logs, with a real time clock for time stamps
AlertsSMS and email alert options on a real time basis
Storage and uptimeEvents stored in an open source database; uptime of at least 99 percent
Fire service linkProvision for an API in future so data can go to the fire service; only critical alarms such as pump power failure, low line pressure and fire alarm fault or fire conditions are to be sent

What are Phase I and Phase II of ACMS?

Both states roll out ACMS in two phases. In Phase I, the system gives the necessary indication to the owner or occupier and to the party responsible for the system: in Maharashtra the Licensed Agency appointed under section 9 of the Act, in Delhi the Fire Safety Auditor engaged under rule 35.

In Phase II, critical alarms are also sent to the fire service: the local fire and emergency services in Maharashtra, and the Delhi Fire Service in Delhi. The rules say Phase I starts with immediate effect when the rules come into force and Phase II will follow at a later stage. Neither text fixes a date for Phase II, so watch for a further notification.

Who can install ACMS and who certifies it?

In Maharashtra, section 10(1) of the Act says no person other than a Licensed Agency shall carry out the work of providing fire prevention and life safety measures, and the Appendix calls the system installer the licensed agency appointed under section 9. Section 3(3A) requires the ACMS to be certified by the Licensed Agency. Under rule 4(3) the agency certifies the installation in Form A-1, and under rule 4(4) it certifies twice a year, in January and July, in Form B-1 that the fire fighting systems are in good repair and efficient working condition with the help of the ACMS. Rule 4(5) lets the owner or occupier submit these certificates to the Chief Fire Officer or Director in person, by registered post, by courier or online.

In Delhi, rule 37 places the duty to provide the ACMS on the owner or occupier, as specified in the Seventh Schedule, and the ACMS schedule routes Phase I indications to the empanelled Fire Safety Auditor engaged under rule 35. Any ACMS in Delhi must also meet the technical standards and cyber security protocols the Director may notify.

A monitoring product can be supplied by any company, but in Maharashtra the installation and the Form A-1 and B-1 certificates must come from a Licensed Agency. Building owners should agree with their agency, before buying, which ACMS the agency will certify.

How does ACMS fit with Form B and the fire audit?

In Maharashtra a section 45(1) building now carries three separate paper trails. Form B, every January and July, certifies that all fire prevention and life safety measures were maintained in the preceding six months. Form B-1, on the same cycle, certifies the fire fighting systems with the help of the ACMS. The Section 45A fire and life safety audit, by a separately licensed auditor, is due once every two years. ACMS data is useful evidence for all three, because it shows what actually happened between inspections.

Sources

  • Maharashtra Fire Prevention and Life Safety Measures Act 2006, section 3(3A): Maharashtra Fire Prevention and Life Safety Measures (Amendment) Act, 2023 (Mah. XXIV of 2023), section 3 (amends section 3); Maharashtra Government Gazette Extraordinary Part VIII, 11 May 2023
  • Maharashtra Act section 3(3A) with Rules rule 3A and rule 4(3) to (5): Maharashtra Fire Prevention and Life Safety Measures Act, 2006 (Mah. III of 2007), s.3(3A) inserted 2023, with rule 3A and rule 4(3) to (5); consolidated from the gazette texts of 2007, 2023 and 2025
  • Maharashtra Act section 45(1), buildings covered: Maharashtra Fire Prevention and Life Safety Measures Act, 2006 (Mah. III of 2007), s.45(1)(a) of 2006 with s.45(1)(b) inserted 2023; consolidated from the gazette texts of 2007, 2023 and 2025
  • Maharashtra Act section 10(1), work only by a Licensed Agency: Maharashtra Fire Prevention and Life Safety Measures Act, 2006 (Mah. III of 2007), section 10(1); as originally enacted, read with the 2023 amendments
  • Maharashtra Rules 2009, rule 3A (inserted 2025): Maharashtra Fire Prevention and Life Safety Measures (Amendment) Rules, 2025, paragraph 4 (amends rule 3); Maharashtra Government Gazette Extraordinary Part IV-B, 12 June 2025, Urban Development Department notification No. MFS-2023/C.R.370/UD-14
  • Maharashtra Rules 2009, rule 4(3) to (5) (inserted 2025): Maharashtra Fire Prevention and Life Safety Measures (Amendment) Rules, 2025, paragraph 5 (amends rule 4); Maharashtra Government Gazette Extraordinary Part IV-B, 12 June 2025, Urban Development Department notification No. MFS-2023/C.R.370/UD-14
  • Maharashtra Rules 2009, Appendix on the Automated Continuous Monitoring System: Maharashtra Fire Prevention and Life Safety Measures (Amendment) Rules, 2025, paragraph 33 (amends Form Y; the Appendix on the Automated Continuous Monitoring System (ACMS)); Maharashtra Government Gazette Extraordinary Part IV-B, 12 June 2025, Urban Development Department notification No. MFS-2023/C.R.370/UD-14
  • Maharashtra Rules 2009, Form A-1: Maharashtra Fire Prevention and Life Safety Measures Rules, 2009, Form A-1 (inserted or substituted 2025); Maharashtra Government Gazette Extraordinary Part IV-B, 23 June 2009, Urban Development Department Notification No. FFS. 2008/CR-181/08/UD-20
  • Maharashtra Rules 2009, Form B-1: Maharashtra Fire Prevention and Life Safety Measures Rules, 2009, Form B-1 (inserted or substituted 2025); Maharashtra Government Gazette Extraordinary Part IV-B, 23 June 2009, Urban Development Department Notification No. FFS. 2008/CR-181/08/UD-20
  • Delhi Fire Service Rules 2010, rule 37 (Automated Continuous Monitoring System): Delhi Fire Service Act 2007 (Delhi Act 2 of 2009), Delhi Fire Service Rules 2010 as amended by the Delhi Fire Service (Amendment) Rules 2025; rule 37; Delhi Gazette Extraordinary Part IV, No. 143, 26 May 2026
  • Delhi Fire Service (Amendment) Rules 2025, rule 1, commencement: Delhi Fire Service Act 2007 (Delhi Act 2 of 2009), Delhi Fire Service Rules 2010 as amended by the Delhi Fire Service (Amendment) Rules 2025; rule 1; Delhi Gazette Extraordinary Part IV, No. 143, 26 May 2026
  • Delhi Fire Service Rules 2010, rule 27, classes of occupancies: Delhi Fire Service Act 2007 (Delhi Act 2 of 2009), Delhi Fire Service Rules 2010 as amended by the Delhi Fire Service (Amendment) Rules 2025; rule 27; Delhi Gazette Extraordinary Part IV, No. 143, 26 May 2026
  • Delhi ACMS schedule, phases and parameters: Delhi Fire Service Act 2007 (Delhi Act 2 of 2009), Delhi Fire Service Rules 2010 as amended by the Delhi Fire Service (Amendment) Rules 2025; rule 3; Delhi Gazette Extraordinary Part IV, No. 143, 26 May 2026
  • Delhi ACMS schedule, procedural requirements: Delhi Fire Service Act 2007 (Delhi Act 2 of 2009), Delhi Fire Service Rules 2010 as amended by the Delhi Fire Service (Amendment) Rules 2025; rule 4; Delhi Gazette Extraordinary Part IV, No. 143, 26 May 2026
  • Delhi Fire Service Rules 2010, rule 35, Fire Safety Auditor: Delhi Fire Service Act 2007 (Delhi Act 2 of 2009), Delhi Fire Service Rules 2010 as amended by the Delhi Fire Service (Amendment) Rules 2025; rule 35; Delhi Gazette Extraordinary Part IV, No. 143, 26 May 2026
  • Delhi Fire Service Rules 2010, rule 2(iv-a), Fire Safety Auditor defined: Delhi Fire Service Act 2007 (Delhi Act 2 of 2009), Delhi Fire Service Rules 2010 as amended by the Delhi Fire Service (Amendment) Rules 2025; rule 2; Delhi Gazette Extraordinary Part IV, No. 143, 26 May 2026

This guide explains the rules in plain words. It is not legal advice; the gazette text and the fire authority decide. A licensed person reviews and signs any submission.

FAQ

Questions people ask

Is ACMS mandatory in Maharashtra?

Yes, for buildings listed in section 45(1) of the Maharashtra Fire Prevention and Life Safety Measures Act: buildings above 30 m used as hotel, hospital, business, mercantile or mixed occupancy, residential buildings above 70 m, refineries and LPG bottling plants, and large moderate or high hazard industrial buildings. The duty is in section 3(3A), and the technical requirements are in the Appendix to the Rules, in force from 12 June 2025.

Is ACMS mandatory in Delhi?

Yes. Rule 37 of the Delhi Fire Service Rules 2010, as amended by the Delhi Fire Service (Amendment) Rules 2025, requires an ACMS for the occupancies in rule 27(2) to (12). The amendment was published on 26 May 2026 and rule 37 commenced 90 days later, on 24 August 2026.

What does ACMS monitor?

Pump run status and power for hydrant, sprinkler, standby, jockey and booster pumps, diesel tank level, hydrant and sprinkler riser pressure, underground and overhead fire tank levels, fire panel detection, panel and battery status, manual call points, the public address system, pressurisation fans and basement supply and exhaust fans. The list is the same in the Maharashtra Appendix and the Delhi schedule.

Who can install ACMS in Maharashtra?

A Licensed Agency. Section 10(1) of the Act reserves the work of providing fire prevention and life safety measures to Licensed Agencies, and the ACMS Appendix names the licensed agency as the system installer. The same agency certifies the installation in Form A-1.

What are Form A-1 and Form B-1?

Form A-1, under rule 4(3), is the Licensed Agency's certificate that the ACMS has been provided on the fire fighting systems. Form B-1, under rule 4(4), is its certificate, given every January and July, that the fire fighting systems are in good repair and efficient working condition with the help of the ACMS.

How often must an ACMS send data?

The rules in both states say the cloud receives data from the IoT gateway at every 1 minute interval, and the cloud must raise an SMS alarm if no data is received for more than 15 minutes.

Does ACMS send alarms to the fire brigade?

Not in Phase I. Phase I indications go to the owner or occupier and the Licensed Agency (Maharashtra) or Fire Safety Auditor (Delhi). In Phase II, critical alarms will also go to the fire service; neither state has fixed a date for Phase II in the rule text.

Does ACMS replace the fire alarm system or Form B?

No. ACMS monitors the existing fire alarm, pumps, tanks and fans; it does not replace them. In Maharashtra the six-monthly Form B and the two-yearly Section 45A audit continue alongside it.